Wreckers Group

Latest Contracts

Willowmoore Cricket Stadium Benoni

Blast this morning 18.08.2019 07h00
Demolition of fourth and final historic light mast situated at Willowmoore Cricket Stadium Benoni.
This mast had a very tight space restriction and accuracy was a key factor.
Carried out by Kyle Perkin, Wreckers Dismantling (Cape) Pty Ltd, who would like to thank everyone involved ensuring a successful operation.

Mittal Van Der Bijl Plate Mill Press

DEMOLITION & REMOVAL OF PLATE MILL PRESS AT MITTAL, VAN DER BIJL UTILISING CUTTING TORCHES & THERMIC LANCES IN FEBRUARY 2019.

Wiilowmoore Park Cricket Stadium

Wreckers successfully carried out the controlled explosive demolition on the 19th November 2018 of the historical Willowmoore cricket masts, situated in Benoni. These masts were constructed during the 1940’s and gave light to one of the first international day/night games.

Headgear Demolition, Shaft 5, Secunda, Wreckers Dismantling

TUT University Demolition of Uncompleted R&I Building Superstructure

Engen New Road Restaurant over N1 Highway called Maxi’s

Both sides of the highway infrastructure had to be demolished, right up to the boundary wall adjacent to the highway. This consisted of the shops, superstructures under highway and the petrol and diesel pump area.

Afrika Widow Movie

Wrecking of old Boeing for a movie shoot simulating a plane crash where actors are placed inside the wreckage.

Rosebank The Galleria Movies

20 Quality Street Isando

Demolition of a single story building including the four story lift shaft and stairwell. The lift shaft and stairwell were separated from the three story building that was to remain and just be stripped out. The demolition works were carried out mechanically using excavators attached with specialized attachments.

Lagos Nigeria Bank of Industries

Nitel Building Implosion – Abuja – Nigeria

Lafarge, Lusaka, Zambia | Controlled Explosives

Mondi, Merebank | Steelwork

Tronox KZN Sands | Heavy Industrial

Sappi Enstra Mill | Springs | Heavy Industrial

Demolition of Pedestrian Over-Bridge on M1

Eskom Grootvlei Power Station – Demolition of Conveyor System and Associated Concrete Plynths

122 Pybus Road Sandton – Implosion of 6 Storey Building

De Beers Mine Kimberley – Demolition of Headgear

Lydenburg Smelter – Furnace Removal

Orlando Power Station Collapse

Xstrata Lydenburg Smelter – Furnace Demolition

Fluor – Vopak Terminal – Island View – Durban

Premier Foods Implosion – Waltloo – Pretoria

Clearing Debris and Supporting Sagging roof after a fire at SABC studio 6 (Isidingo)

Nedbank Gardens Implosion – Rosebank – South Africa

Lancing of Slag Iron for Furnace Wrecking – Highveld Steel – South Africa

Get in touch

We would love to hear from you! Please fill out this form and we will get in touch with you shortly.
  • This field is for validation purposes and should be left unchanged.